Projects

South East Construction has worked on numerous construction and maintenance projects directly for owners like SaskPower, PCS, Mosaic, Saskferco, Prairie Mines and Royalties, Bunge, Roblin Forest Products and others. We have also worked extensively for EPCM firms such as AMEC, Hatch and SNC Lavalin and as a subcontractor on major construction sites for WSIndustrial, Diaser Management, Comstock, Graham, Magna, Westwood, Promec, Pyramid, PCL and numerous others.

Some of our projects include:

SaskPower

2001-2014 - Shand, Poplar River and Boundary Dam sites: coal handling upgrades including structural and cladding on galleries, precipitator improvements and equipment sealing upgrades, pump house travelling screen replacements, boiler house structural steel upgrades, ash system and galleries, structural and mechanical upgrades, feed water heater structural steel upgrades, new sampler building and equipment, boiler rebuild access - including monorail installation/removal, structural steel removal/replacement as well as numerous piping and mechanical projects. E.B. Campbell Dam - monorail and stop log replacements and upgrades. Tazin lake Tunnel complete Dam refurbishment, Individual contracts range in value from $25k to $3M.

Mosiac Esterhazy- K1-K2-K3

2001-Current - Numerous structural steel upgrades and new installations, including: mill, shop, headframe, cranes (surface and underground), galleries, bins, loading pockets. Demolition projects including total demolition of Crystallizer building and all tanks, pumps, underground bins & mechanical, piping and equipment. Site Services and Maintenance.

PCS Rocanville

2002-Current - Miscellaneous projects including bin and structural steel upgrades underground, thickener building glycol system fabrication and installation, screen support steel upgrades, pumphouse demolition and new pumphouse installation, brine line fabrication and installation, red dye addition system, and others. Individual contracts ranged from $20k to $9M.

AMEC at Rocanville

Ongoing work - Chute modifications, derrick screen assemblies, and other miscellaneous projects.

SNC Lavalin

2009 - Mosaic K2 site - supply and install of substation buildings (2) and mechanical installation for both as well as hoisting of transformers and critical electrical components approximate value of contracts - $1,900,000.

BHP / SNC Lavalin

2011 to Current- Site services contract as well numerous ongoing contracts such as road building, pond construction, Water and Hydrovac, concrete foundations and land management.

Mosaic Colonsay

May 2011 to Ongoing - Site & maintenance services, earthworks, electrical, general contracting, electrical cable tray and steel contracts. We are working with Hatch and Mosaic for this project.

K2 Hatch & Mosaic

2009 to Ongoing - Mosaic K2 expansion, site services, general contracting, wet area structural upgrades - $12,500,000, Wet area mechanical upgrades - $13,000,000, Crushing structural and bin upgrades - $6,000,000, Crushing mechanical upgrades - $6,000,000, Dry area upgrade assistance = $2,000,000, Miscellaneous construction assistance - $1,000,000

Mosaic K3

August 2011 to Ongoing - Site services, general contracting, piping and civil contracts.